Business Start Up Time Line (3 pages)

BENCHMARK/ACTION PROCESS/ACTION START – END DATE
     
  SECURITY & SURVEILLANCE  
1.     Form Security Team Team members will be hired/vetted, & input for system documented Jan 1–14
2.     Create preliminary floorplan Team works with architect to create preliminary dispensary design/review & system requirements per 3796:6-2-02-B-8 Jan 15-21
3.     Request bids System documentation & requirements sent out in bid form Jan 22-27
4.     Evaluate/compare

bids

Receive bids, create matrix for price, overall equipment quality, ability to satisfy state requirements Feb 3-10
5.      Contact bidder references Speak to past customers, review online reviews, contact equipment vendors Feb 11-15
6.      Select bidder Finish grading matrix, score vendors Feb 16-20
7.     Sign contract with vendor Negotiate contract with selected vendor Feb 21-24
8.     Vendor work begins Vendor begins installing conduit & equipment Mar 1-7
9.     Vendor work finished & approved Cameras & alarms tested, off side data cloud system tested & approved Mar 10